FiscalSystems-RETL (ERP) Project Weekly Status Call
Aug 15
21m
Action Items
Contact James about adding additional QA resource to project
Talk to James and send email about adding a second QA resource to assist with testing workload, as the current single QA resource is overwhelmed with multiple concurrent module releases.
Create Excel sheet for tracking QA feedback across releases
Create an Excel spreadsheet with separate tabs for each QA release (QA1, QA2, QA3, etc.) to track and organize feedback points, including summaries where possible to avoid losing information in emails.
Address feedback communication process with UI/UX team
Prioritize discussion with UI/UX team about improving communication back to Lawrence and Manisha regarding their feedback on development calls, ensuring they receive responses about what changes will or won't be implemented.
Provide workflows for all completed modules
Share process flows and workflows for all completed modules by next week to help Lawrence and Manisha understand module functionality, including where processes start, end, and how pages connect.
Update project plan with current status
Update and share the project plan by next week showing what has been completed, what is currently in progress, and what is pending for phase one completion by October trade show.
Overview
Lawrence agreed to request an additional QA resource from James to support the overwhelmed single QA person currently handling 4-5 modules concurrently
Chetu committed to provide process workflows and updated project status by August 22nd, 2025 to clarify what's completing in phase one by the October trade show deadline
Manisha highlighted major UI usability issues where editing requires 5-6 minutes for 2-3 fields due to page closing after each update
Shankar agreed to fix UI/UX feedback communication gaps where suggestions aren't being addressed or communicated back to Fiscal Systems
Additional QA resource request
Shankar explained their single QA resource is overwhelmed with 4-5 modules releasing concurrently as phase one nears completion
Lawrence agreed to email James immediately to request a second QA person, expecting response by August 22nd, 2025
Chetu plans to split QA work with one person focused on regression testing and another on new feature testing
Lawrence noted the current setup leaves no coverage for sick days or breaks
Process workflow documentation needs
Manisha requested process flows for each module showing start-to-end functionality and page connections
Fiscal Systems currently tests based on assumptions without knowing module workflows or interdependencies
Shankar committed to provide workflows for all completed modules and updated project status by August 22nd, 2025
Manisha needs this information to update internal teams and James on phase one completion scope
User interface usability concerns
Manisha identified editing issues requiring 5-6 minutes to update 2-3 fields because pages close after each individual field update
Current process requires reopening pages and clicking edit for each field modification
Manisha noted concern about scalability when master data contains thousands of entries
No import options currently available for master data pages
Manisha agreed to create an Excel sheet with tabs for each QA release to track feedback systematically
UI/UX feedback communication gaps
Manisha and Lawrence provide suggestions during development calls but see no changes implemented in subsequent releases
Shankar explained Ravi typically verifies feedback against UI/UX documentation and communicates with the UI/UX team
Shankar committed to address the UI/UX team's lack of follow-up communication on feedback decisions
Agreement that UI/UX team should discuss feedback responses during calls rather than leaving Fiscal Systems uninformed
Testing coordination improvements
Shankar committed to provide clearer release documentation including interdependencies and specific testing scope
Lawrence clarified Fiscal Systems will continue comprehensive UAT testing since they're the customer contact point
Agreement to hold meetings after each QA release cycle for better feedback communication
Manisha prefers meetings over email for complex UI/UX feedback explanations